Posts Tagged ‘three-point estimates’

Avoid the Most Common Estimating Mistake

19 May 2009

Three-Point EstimatesDon’t ask “How long will this task take?” because the customary response will be the “most likely” estimate without considerations for the best-case and worst-case scenarios.

A staff may pad a two-day task to 2.5 days “just to be safe.” His team leader may add a day for “good measure” with the manager “blindly” tacking another 10-15% contingency. With this nonsense, the final estimate can easily become 100% more than the original!

It is better to ask for raw optimistic (O), most likely (M) and pessimistic (P) estimates—along with the assumptions. Manage the project based on the “weighted” expected (E) estimates with a contingency of ± three standard deviations (±3S). If the standard deviation is too wide, scrutinize the assumptions and revise the estimates.

E = (O + 4M + P) / 6
S = (P – O) / 6

Connect with Dr. John A. Estrella via Facebook, LinkedIn and Twitter.

How do you make your contingency reserves 99.73% accurate?

7 April 2009

Three-Point EstimatesUse three-point estimates to make contingency reserves more accurate

Duration and cost estimates can be greatly improved by incorporating uncertainty and risks. Unfortunately, some project managers simply pick an arbitrary percentage when allocating contingency reserves (e.g., 10% or 25% of the total duration or cost).

For each project activity, ask your team members to provide three estimates: most likely (tM), optimistic (tO) and pessimistic (TM). You can do this for duration only, cost only or both. Use PERT analysis to calculate the expected value (tE) using the formula tE = (tO + 4tM + tP) / 6. Calculate the standard deviation (tS) = (tP – tO) / 6.

Manage your project based on tE. Your contingency reserve should be +/- 3tS. In doing so, statistically, there is a 99.73% probability that the duration or cost will fall within tE +/- 3tS.

Connect with Dr. John A. Estrella via Facebook, LinkedIn and Twitter.

Three-Point Estimates in Microsoft Office Project

22 March 2009

Connect with Dr. John A. Estrella via Facebook, LinkedIn and Twitter.